|
Redstone Mine
Liberty declared the Redstone nickel mine to be in commercial production on July
1, 2007 at a target rate of 200 tonnes per day. Underground drilling was
completed in April 2007 to the 508m level to enable a National Instrument
43-101 resource calculation to be done. A measured (274,085 tonnes) and
indicated (144,846 tonnes) resource of 418,931 tonnes grading 2.32% nickel
("Ni") to and above the 508m level of the mine was released on December 18, 2008.
An updated 43-101 technical report is scheduled to be released in 2009. Construction of
the shaft surface infrastructure is complete. Once the shaft is sunk to the
1150m level, the deeper mineralization can be mined at a reduced cost and increased
tonnage.
Eleven boreholes drilled in 2007 from the 789m to 1155m levels have confirmed a
large section of the “Inco Anomaly” tested within the Redstone channel (see
Redstone Project) is a nickel bearing orebody. More drilling is required to
test the entire extent of the geophysical anomaly below 1150m and further to
the west at depth. Some highlights of the deep drilling include:
- 3.45m of 3.9% Ni at the 675m level;
- 8.5m of 2.4% Ni at 789m below the surface; and
- 4.65m of 3.62% Ni encountered 1064m below the surface.
The 2000 tonne per day Redstone nickel concentrator was commissioned in July
2007. It will initially operate at approximately 450 tonnes per day until the
McWatters nickel mine ramps up to full production in the fourth quarter of
2008. The mill contains a sophisticated flotation circuit to effectively
separate nickel sulphides from the high magnesium hydroxide (talc) component
typical of altered komatiite nickel mineralization in the Shaw Dome Nickel Belt. It is
fully automated including an online analyzer which can isolate both light and
heavy elements. It also contains a gravity circuit to enhance the payable
amounts for platinum, palladium and gold.
Liberty ships its nickel in concentrate to Jilin Jien Nickel Industry Company
Ltd. of China and to Xstrata Nickel’s smelter in Sudbury, Ontario.
McWatters Mine
Construction began in mid November 2007 at the McWatters nickel mine, located
approximately 9 km to the east of the Redstone Mine. A
43-101 technical report was released December 18, 2008 which stated an indicated resource
of 665,308 tonnes of ore grading 0.72% Ni in the upper zone and 49,562 tonnes
grading 3.93% Ni in the lower zone with an inferred resource of 13,829 tonnes
grading 3.39% Ni in the lower zone. An updated technical report is scheduled to be released in
the spring of 2009.
Hart Mine
Permitting is underway for Liberty’s third nickel mine at the Hart project,
located 7 km east of the Redstone site. A NI 43-101 resource calculation
released on October 20, 2008 stated an indicated resource of 1,390,000 tonnes
grading 1.50% Ni and 0.1% Cu and an inferred resource of 286,000 tonnes grading
1.36% Ni and 0.09% Cu. These tonnages represent the largest NI 43-101 compliant
resource in the Shaw Dome identified to date with an average grade of 1.5% Ni.
The resource calculation included drilling only to the 460m level. Mineralization
is also known to exist down to the 550m level, so additional deep drilling will attempt to extend the resource at depth.
A geophysical survey to further elucidate drill targets for the entire Shaw Dome
was completed in Q1 2008. Many targets have been elucidated and drilling will
be ongoing for the next several years. Management is excited about the
prospects of making new discoveries on its prospective mining claims in the
Shaw Dome Nickel Belt.
Groves Nickel Copper PGM Project
An airborne VTEM survey was complete in Q1 2008. In addition to the historically
known resource (see Groves Project), three outstanding targets have been located and an extensive
drill program will begin in late 2008. Some historical drill cores reported 5 g/t of iridium, which
indicates the potential of the deposit as a source of this rare element.
Investment Highlights
-
Liberty currently has three nickel mines to feed its 2000 tonne per day nickel
concentrator: one in commercial production, a second to be declared in
commercial production in the fall of 2008 and a third to be brought into
pre-production in 2009.
-
The Company has four major exploration areas consisting of contiguous mining
claims and leases with known mineralization and excellent potential for
additional discoveries.
-
Liberty's NI 43-101 nickel resource base is quickly growing.
-
Liberty has the potential to be a mid tier producer of nickel with significant copper and PGM credits
and to develop a primary resource of cobalt.
-
Liberty Mines Inc. will soon be acknowledged in the financial community for its
substantial fast paced achievements and development of positive cash flow.
-
Cash flow will increase substantially in 2009 as Liberty becomes a mid tier
producer of nickel.
Market Data
Trading symbol LBE on the Toronto Stock Exchange
Shares Outstanding as of
07/25/08 82,370,694
Warrants from Financings
12,197,322
Stock
Options
4,743,639
Fully
diluted
99,311,655
Analyst Coverage
Analyst
Institution
Target/Recommendation
Pat Donnelly Salman
Partners $1.05 Buy
|
|

Property Locations in Ontario, Canada

Liberty’s Mining Claims in the Shaw Dome
Nickel Belt

Floatation of Nickel in Concentrate at
the Redstone Mill
Sothman Nickel Project
The Sothman nickel copper deposit, located approximately 75 km south of Timmins
Ontario, was optioned from Xstrata. The deposit contains an historical resource as
reported by Falconbridge Nickel 1971 (see Sothman Project). Exploration at the property began in June 2008.
McAra Lake Cobalt Project
The cobalt deposit at McAra Lake consists of rich veins of cobaltite typically
grading up to 11% cobalt over 1m-1.5m with intersections of 19.46m averaging
1.1% cobalt. It also contains significant copper with intersections of
chalcopyrite containing 11.9% copper over 3.1m as well as varying credits of
nickel up to 1%.
The McAra Lake cobalt deposit offers Liberty the potential to develop a primary
resource of cobalt. The adjacent Ray Township properties have many surface pits
that may also develop similarly. A drill program is
scheduled to commence in 2008 to further develop these two contiguous
properties.
Management
Dr. Gary Nash BSc PhD (Physics), President and CEO
Will Randall BSc MSc (Geology) VP Exploration
Bob Bresee Mine Manager
Jason Cyr Mill Manager
Mike Pommer IT/IS Manager
Directors
Dr. Gary Nash BSc PhD (Physics)
Don Schurman BCom MHSA
John Pinsent BCom CA
Gerry Feldman BCom (Hons) CA
Steve Anderson Geophysics Consultant
Gil Bertrand Mine Health and Safety Consultant
Head Office
311A 8925-51 Avenue
Edmonton, Alberta,T6E 5J3
Phone:780-485-2299 Fax: 780-485-22253
Redstone Mine Site
Box 398 South Porcupine, Ontario, PON 1H0
Phone: 705-240-6450 Fax: 705-240-6451
|